About Scott Middle School

PROJECT LOCATION

Lincoln, Nebraska

Problem

New improvements to a middle school in Lincoln Nebraska included an existing wall that would need to be backfilled 3’ above its original foundation potentially causing an excess of lateral pressure on the existing wall.

The Solution

In order to reduce the increased pressure from the wall, 35 PCF lightweight cellular concrete was placed to an average depth of 3’-0”. 100Cy of material were easily pumped into place in an hour using a small towable pump using a “wet” mix method.