Mission Trails Regulatory Structure II and Flow Control Facility

https://www.cell-crete.com/build/wp-content/uploads/2022/12/Missiontrailswebsite.jpg

Project: Mission Trails Regulatory Structure II and Flow Control Facility

Title:

Description:

Mission Trails Regulatory Structure II and Flow Control Facility

Missiontrailswebsite.jpg

Mission Trails Regulatory Structure II and Flow Control

PROJECT LOCATION

San Diego, CA

The Project

Cell Crete’s scope of work on this project included the abandonment of portions of existing pipelines 3 and 4. Class II cellular concrete was selected as the backfill material to abandoned the existing waterlines. A 69” and a 72” pipe were abandoned each were roughly 1000’ in length, in the end we ended up placing over 2500CY in just under 4 days.