Palos Verdes, CA
The work consists of rehabilitation of approximately 6,500 linear feet of prestressed concrete cylinder pipe (PCCP) and installing a steel liner pipe. This is Phase A of this project phase B will be completed later this year and will be roughly 19,000LF.
The (e) PCCP was 78″ the steel liner was 75″, Class VI cellular ocncrete was used to grout the annular space between the new steel line and the PCCP pipe.