Flume 4,5,6 & 30 LCC Fill

https://www.cell-crete.com/build/wp-content/uploads/2022/06/IMG_0875.jpg

Project: Flume 4,5,6 & 30 LCC Fill

Title:

Description:

Flume 4,5,6 & 30 LCC Fill

IMG_0875-1200x900.jpg

Flume 4,5,6 & 30 LCC Fill

PROJECT LOCATION

Tahoe, CA

The Project

Emergency projects to rebuild and repair the water delivery system after the Caldor Fire. The Caldor Fire overtook more than 220,000 acres of area, some sections of El Dorado Canal that delivers water supplies from high elevation lakes, specifically Flumes 4, 5, 6 & 30, were destroyed.

The Solution

It was very tight access to the job site. The engineer was looking for a lighter and stronger fill material to prevent the landslide. The plan was to have the material exposed permanently. We proposed our class II material with fibermesh and concrete sealer in order to prevent cracking and to prevent any water to penetrate the LCC.